08 04 06
Tracy Young Kennedy Space Center, Fla 321-867-2468
STATUS REPORT: S-080406
NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT
Note: NASA's Kennedy Space Center issues Space Shuttle Processing
Status Reports periodically and is the source for information
regarding processing activities associated with the vehicles and
payloads
This report does not necessarily reflect the chronological
order of future space shuttle missions
If you are a member of the
media and would like further information, visit:
http://www
nasa
gov/centers/kennedy/news/index
html
Mission: STS-115 - 19th International Space Station Flight (12A) - P3/P4 Truss Segment and Solar Arrays Vehicle: Atlantis (OV-104) Location: Launch Pad 39B Launch Date: No earlier than Aug 27, 2006 Launch Pad: 39B Crew: Jett, Ferguson, Tanner, Burbank, MacLean and Stefanyshyn-Piper Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Early on Wednesday, Space Shuttle Atlantis rolled from high bay 3 in the Vehicle Assembly Building to Launch Pad 39B Early Thursday, the orbiter's auxiliary power units were successfully test fired Also on Thursday morning, the rotating service structure was moved to the mate position and is now surrounding the orbiter as it sits on the mobile launch platform Functional tests and checkout of the shuttle and pad systems are under way
The STS-115 payload is scheduled to be installed in Atlantis' payload bay on Saturday The payload for STS-115 is the Port 3/4 truss segment, the next major addition to the 11-segment integrated truss structure that will eventually span more that 300 feet The P3/P4 truss, with its two large solar arrays, will provide one-fourth of the total power generation capability of the completed station
Mission managers made the decision to move the opening of Atlantis' launch planning window to Aug 27 The decision was made after it was determined that lighting conditions for launch and external tank separation were sufficient to support imagery analysis
Next week, the STS-115 crew will visit KSC for a launch dress rehearsal, called the terminal countdown demonstration test
Mission: STS-116 - 20th International Space Station Flight (12A 1) - P5 Truss Segment Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: No earlier than Dec 14, 2006 Launch Pad: 39B Crew: Polansky, Oefelein, Curbeam, Higginbotham, Patrick and Fuglesang
Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Processing of Discovery for its next mission, STS-116, continues in Orbiter Processing Facility bay 3 Following discovery of a leak, fuel cell no 2 was removed and replaced Work is under way to remove and replace the L5L vernier thruster, located on the portside orbital maneuvering system pod, following a thruster heater malfunction during the STS-121 mission Windows no 1, 2 and 5 have been replaced, with replacement of windows no 3 and 4 to follow this week The orbiter boom sensor system was re-installed Thursday after completion of post-flight inspections Post-flight inspection of the thermal protection system is 90 percent complete
Endeavour (OV-105)
Powered-up system testing continues on Endeavour in Orbiter Processing Facility bay 2 following an extensive modification period Workers performed brake leak checks, main propulsion actuator leak checks and environmental control life support system rotary equipment checks this week Fuel tank installation for the power reactant storage and distribution (PRSD) system is under way Oxygen tank no 5 will be installed Monday The PRSD supplies liquid hydrogen and liquid oxygen to the orbiter's fuel cells, which serve as the electrical power plant for the vehicle The seats for the shuttle crew commander and pilot were installed in the flight deck this week Testing of the atmosphere revitalization pressure control system was completed this week
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: BULK_EMAIL
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]
If you're still having trouble, please contact the list owner at:
<mailto:list
admin@aus-city
com>
The following physical address is associated with this mailing list:
http://www aus-city com
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list