George Diller Kennedy Space Center, Fla 321-867-2468

STATUS REPORT: S-033007

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads If you are a member of the media and would like further information, visit:
http://www nasa gov/centers/kennedy/news/index html

Mission: STS-117 - 21st International Space Station Flight (13A) - S3/S4 Truss Segment Solar Arrays Vehicle: Atlantis (OV-104) Location: Vehicle Assembly Building Launch Date: Targeted for April 2007 Launch Pad: 39A Crew: Sturckow, Archambault, Reilly, Swanson, Forrester and Olivas Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

In high bay No 1 of the Vehicle Assembly Building, work is under way to assess and repair hail damage to the STS-117 external fuel tank, ET-124 Special scaffolding and access platforms have been erected to allow access to the tank and orbiter for inspections and repairs Foam repairs on the liquid hydrogen tank, which is located on the bottom of the external tank, are complete The focus is currently on repairs to the liquid oxygen tank

Shuttle program managers will meet on or about April 10 to decide whether to use ET-124 or substitute it with a new tank, ET-117, which is scheduled to arrive at KSC in early April

Mission: STS-118 - 22nd International Space Station Flight (13A 1) - S5 Truss Segment Vehicle: Endeavour (OV-105) Location: Orbiter Processing Facility Bay 2 Launch Date: Targeted for June 28, 2007 Launch Pad: 39A Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Anderson Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Endeavour remains in Orbiter Processing Facility bay 2, and technicians continue preparing the vehicle for its first launch in more than four years The vehicle has undergone an extensive modification period, including the addition of all of the return-to-flight safety upgrades added to both Discovery and Atlantis

This week, initial nose landing gear door closure was performed Preparations are under way for the installation next week of the orbiter boom sensor system, which is a 50-foot extension for the shuttle's robotic arm Technicians completed testing the audio/visual communications systems on the orbiter The shuttle main engine "eyelids," which are thermal barriers that protect the aft compartment, were installed Preparations are under way for the installation of the engine mounted heat shields

Mission: STS-122 - 24th International Space Station Flight (1E) - Columbus Laboratory Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: Targeted for Fall 2007 Launch Pad: 39-A Crew: Frick, Poindexter, Walheim, Love, Melvin, Schlegel and Eyharts Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Processing of Discovery, which returned from the STS-116 mission on Dec 22, continues in Orbiter Processing Facility bay 3

The installation of the new station-to-shuttle power transfer system was completed this week This system will allow the orbiter and International Space Station to share power, enabling the orbiter to remain docked for longer periods of time

The orbiter power system validation was also finished this week Technicians continue replacing thermal tile around the main landing gear door and the external tank doors with a stronger tile, known as BRI tile

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list