Date: May 19th 2007

05 18 07

George H Diller Kennedy Space Center, Fla 321-867-2468

STATUS REPORT: ELV-051807

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Dawn Location: Astrotech Space Operations Facility Launch Pad: 17-B Launch Vehicle: Delta II 7925-H Launch Date: Target June 30, 2007 Launch Window: 5:13:15 p m EDT

Preparations are under way for moving the Dawn spacecraft to an adjacent clean room high bay for solar array integration

Next week, the two spacecraft solar arrays, each consisting of four panels, will be attached to the Dawn spacecraft and undergo deployment testing A solar array lighting test also will be performed before the arrays are stowed for flight This activity is scheduled for May 21-24

The spacecraft will be moved to Astrotech's Hazardous Processing Facility for fueling on May 26

The Delta II first stage will be hoisted into the launcher at Pad 17-B on May 23 and attachment of the nine solid rocket boosters will begin

Mission: Phoenix Location: Payload Hazardous Servicing Facility Launch Pad: 17-A Launch Vehicle: Delta II 7925 Launch Date: Aug 3, 2007 Launch Time: 5:35:18 a m EDT

The dry spin test of the spacecraft was successfully completed A heat shield deployment test also was successfully conducted Wednesday

The electrical power system final performance test was completed Thursday

The flight software will be loaded aboard the spacecraft on May 21

Compatibility testing with the Deep Space Network is scheduled for May 23-25

In Hangar AO at Cape Canaveral Air Force Station, gimbal slew tests of the Delta II first-stage main engine will be conducted next week These are main engine steering checks using the first-stage hydraulic systems

Previous status reports are available on the Web at:

http://www nasa gov/centers/kennedy/launchingrockets/status/2007

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list