05 25 07
George Diller Kennedy Space Center, Fla 321-867-2468
STATUS REPORT: S-052507
NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT
Note: NASA's Kennedy Space Center issues Space Shuttle Processing
Status Reports periodically and is the source for information
regarding processing activities associated with the vehicles and
payloads
If you are a member of the media and would like further
information, visit:
http://www
nasa
gov/centers/kennedy/news/index
html
Mission: STS-117 - 21st International Space Station Flight (13A) - S3/S4 Truss Segment Solar Arrays Vehicle: Atlantis (OV-104) Location: Launch Pad 39A Launch Date: Targeted for June 8, 2007 Crew: Sturckow, Archambault, Reilly, Swanson, Forrester, Olivas and Anderson Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
At Launch Pad 39A, operations are proceeding on schedule for a June 8 launch This week, the hypergolic propellants were loaded into the orbiter and solid rocket boosters Extra Vehicular Mobility Unit Nos 1 and 2 (space suits) were installed in the orbiter airlock Functional testing of the external fuel tank camera is complete, and the lens cover has been installed Loading of the liquid oxygen and liquid hydrogen storage tanks, which will provide fuel for the shuttle's external fuel tank, is complete
A Flight Readiness Review, a two-day meeting to assess preparations for Atlantis' mission, will be held on May 30-31
Mission: STS-118 - 22nd International Space Station Flight (13A 1) - S5 Truss Segment Vehicle: Endeavour (OV-105) Location: Orbiter Processing Facility Bay 2 Launch Date: Targeted for Aug 9, 2007 Launch Pad: 39A Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Drew Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Endeavour's payload bay closeouts are complete, and the payload bay doors were closed for rollover to the Vehicle Assembly Building The strongbacks, which are used to support the doors, have been removed Preparations are under way for the landing gear functional test, which is scheduled for next week System checks are under way, with the Forward Reaction Control System thruster verification complete
In high bay No 1 of the Vehicle Assembly Building, stacking of the solid rocket boosters for STS-118 has begun The left aft and the right aft sections of the boosters were lifted into the bay Wednesday and Thursday The left aft center segment will be lifted into the bay Friday night
Mission: STS-120 - 23rd International Space Station Flight (10A) - U S Node 2 Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: Targeted for Oct 20, 2007 Launch Pad: 39A Crew: Melroy, Zamka, Parazynski, Wheelock, Wilson, Nespoli and Tani Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Inspections of Discovery's gap fillers, which are located between the thermal tiles, are complete Testing of the Shuttle to Station Power Transfer System is under way Power Reactant Storage and Distribution System testing is complete Functional testing of the atmospheric revitalization pressure control system, part of the orbiter's life support system, continued this week Modifications to Discovery's engine cutoff sensor wiring continue, as does the installation of BRI tile around the main landing gear doors and external tank doors
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: example@example.com
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]
If you're still having trouble, please contact the list owner at:
<mailto:list
admin@aus-city
com>
The following physical address is associated with this mailing list:
http://www aus-city com
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list