Date: November 22nd 2007

Nov 21, 2007

Candrea Thomas Kennedy Space Center, Fla 321-867-2468 candrea k thomas@nasa gov

STATUS REPORT: S-112107

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads If you are a member of the media and would like further information, visit:
http://www nasa gov/centers/kennedy/news/index html

Mission: STS-122 - 24th International Space Station Flight - Columbus Module Vehicle: Atlantis (OV-104) Location: Launch Pad 39A Launch Date: Targeted for Dec 6, 2007 Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Last weekend, engineers and technicians successfully resolved an issue with a stuck valve in Atlantis' forward reaction control system, isolating the problem to a broken ground lug in the helium isolation valve circuit Repairs were made and the valve is now functioning normally Throughout the week, workers continued to validate shuttle/pad connections, and orbiter aft closeout work begins Nov 28 Because no major issues are being worked and processing has been going well, teams will have Thanksgiving Day through Sunday off

On Saturday, Nov 17, the STS-122 crew arrived at Kennedy Space Center for the terminal countdown demonstration test, or TCDT, which included a countdown dress rehearsal and a training exercise The crew returned to NASA's Johnson Space Center Tuesday following the TCDT's successful conclusion

Mission: STS-123 - 25th International Space Station Flight - Kibo, Dextre Vehicle: Endeavour (OV-105) Location: Orbiter Processing Facility Bay 2 Launch Date: Targeted for Feb 14, 2008 Launch Pad: 39A Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

In Orbiter Processing Facility bay No 2, integrated testing of the main engines and the main propulsion system continues Testing of the orbiter's three-string GPS system, which provides guidance on re-entry, is complete

The star tracker door functional test is complete Window No 7 has been removed and replaced The payload bay door functional test is finished Installation of BRI tile around the perimeter of the right main landing gear door is finished Checkout of the Shuttle to Station Power Transfer System is complete

In high bay No 1 of the Vehicle Assembly Building, stacking of the left solid rocket booster is under way Stacking of the right booster is scheduled to begin next week

Mission: STS-124 - 26th International Space Station Flight - Kibo Pressurized Module, Japanese Remote Manipulator System Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: Targeted for April 24, 2008 Launch Pad: 39A Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

In Orbiter Processing Facility bay No 3, hypergolic fuel has been off-loaded from the orbital maneuvering system Inspections of the reinforced carbon-carbon panels on the wing leading edges are complete The main engine dome heat shields have been removed, and preparations are under way for removal of the three main engines next week Functional checkout of the forward reaction control system is in progress, and window No 1 has been removed and replaced Post-flight inspection of the thermal protection system is 70 percent complete

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list