Date: March 28th 2009

March 27, 2009

George H Diller Kennedy Space Center, Fla 321-867-2468 george h diller@nasa gov

STATUS REPORT: ELV-032709

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Geostationary Operational Environmental Satellite (GOES-O) Launch Vehicle: Delta IV Launch Pad: Launch Complex 37, Cape Canaveral Air Force Station, Fla Launch Date: No earlier than April 28, 2009 Launch Window: 6:24 - 7:24 p m EDT

The spacecraft was placed on a special stand on March 22 for propellant functional testing and fueling preparations A second check with the Delta IV payload attach fitting is planned for March 28 The loading of hydrazine currently is scheduled for March 30 Mating GOES-O to the Delta IV payload attach fitting for flight is planned for April 3 and will be followed by encapsulation into the fairing on April 6 The move to Launch Complex 37 for mating to the Delta IV is scheduled for April 14

At Launch Complex 37, checkout of the Delta IV and associated prelaunch preparations are on schedule A simulated flight test exercising the launch vehicle systems as they will function during launch is under way today The "wet dress rehearsal," a countdown dress rehearsal with the rocket fully fueled, is planned for April 8

NASA has contracted with Boeing to build and launch the GOES-O spacecraft The NASA Launch Services Program at Kennedy is supporting the launch in an advisory role NASA spacecraft project management for GOES-O is the responsibility of NASA's Goddard Space Flight Center After launch, once Boeing and NASA have completed checkouts in orbit and the spacecraft is operational, it will be turned over to NOAA

Mission: Lunar Reconnaissance Orbiter/Lunar Crater Observation and Sensing Satellite (LRO/LCROSS) Launch Vehicle: Atlas V Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla Launch Date: May 21, 2009 Launch Window: 5:32 - 6:32 p m EDT

This week LRO performed an integrated launch simulation Thermal blanket installation on the spacecraft continues

The Atlas V is planned to be moved from the hangar at the Atlas Space Operations Center to the Vertical Integration Facility at Launch Complex 41 on or about April 10

Previous status reports are available at:

http://www nasa gov/centers/kennedy/launchingrockets/status/index html

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

<[program_url]/list/[list]>

If you're still having trouble, please contact the list owner at:

<mailto:[list_owner_email]>

The following physical address is associated with this mailing list:

[physical_address]

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list