May 8, 2009
George H Diller Kennedy Space Center, Fla 321-867-2468 george h diller@nasa gov
STATUS REPORT: ELV-050809
EXPENDABLE LAUNCH VEHICLE STATUS REPORT
Mission: Geostationary Operational Environmental Satellite (GOES-O) Launch Vehicle: Delta IV Launch Pad: Launch Complex 37, Cape Canaveral Air Force Station, Fla Launch Date: No earlier than June 2009 Launch Window: TBD
The GOES-O launch aboard a Delta IV rocket from Space Launch Complex 37 currently is scheduled for no earlier than June 26 Recent production lot testing of the linear shape charge system indicated the need to incorporate minor design changes to assure their reliability The linear shape charge is a component of the Range Safety command destruct system There are three linear shape charges on this Delta IV which will require a modification Schedules are being developed for the qualification and implementation of the design modification
At the Astrotech Space Operations Facility, the GOES-O spacecraft is enclosed in the payload fairing The spacecraft remains in excellent health and is ready to be moved to the launch pad once a launch date has been determined
NASA has contracted with Boeing to build and launch the GOES-O spacecraft The NASA Launch Services Program at Kennedy is supporting the launch in an advisory role NASA spacecraft project management for GOES-O is the responsibility of NASA's Goddard Space Flight Center After launch, once Boeing and NASA have completed on-orbit checkout and the spacecraft is operational, it will be turned over to NOAA
Mission: Lunar Reconnaissance Orbiter/Lunar Crater Observation and Sensing Satellite (LRO/LCROSS) Launch Vehicle: Atlas V Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla Launch Date: No earlier than June 2, 2009 Launch Window: TBD
Tuesday, the LRO and Kennedy Space Center Boeing fueling team configured the fueling ground support equipment for propellant loading The LCROSS team moved the battery simulator to the Atlas V payload van
On May 2, the LRO team performed a pressurization test, a leak test and a latch valve leak test
The Atlas V booster stage was moved from the hangar at the Atlas Space Operations Facility to the Vertical Integration Facility near the launch pad on April 27 The Centaur was moved on April 29 and hoisted atop the Atlas
The LCROSS spacecraft was fueled on April 25 LRO fuel loading was completed on May 5
The three solar arrays were attached to LRO on April 19 Spacecraft testing during the week of April 20 included a circuit check of the solar arrays, a course sun sensor functional test, and phase testing of the attitude control system
Previous status reports are available at:
http://www nasa gov/centers/kennedy/launchingrockets/status/index html
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: example@example.com
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
<[program_url]/list/[list]>
If you're still having trouble, please contact the list owner at:
<mailto:[list_owner_email]>
The following physical address is associated with this mailing list:
[physical_address]
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list