Date: August 12th 2006

08 11 06

Bruce Buckingham Kennedy Space Center, Fla 321-867-2468

STATUS REPORT: S-081106

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads This report does not necessarily reflect the chronological order of future space shuttle missions If you are a member of the media and would like further information, visit:
http://www nasa gov/centers/kennedy/news/index html

Mission: STS-115 - 19th International Space Station Flight (12A) - P3/P4 Truss Segment and Solar Arrays Vehicle: Atlantis (OV-104) Location: Launch Pad 39B Launch Date: No earlier than Aug 27, 2006 at about 4:30 p m EDT Crew: Jett, Ferguson, Tanner, Burbank, MacLean and Stefanyshyn-Piper Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

At Launch Pad 39B, functional tests and checkout of the shuttle and pad systems are under way Installation of the elbow camera of the orbiter's remote manipulator system (robotic arm) is complete This weekend, hypergolic propellant loading will begin for the orbiter's reaction control system, orbital maneuvering system pods and the auxiliary power units, and for the hydraulic power units of the solid rocket boosters

The STS-115 payload was installed in Atlantis' payload bay last Saturday The payload for STS-115 is the Port 3/4 truss segment, the next major addition to the 11-segment integrated truss structure that will eventually span more that 300 feet The P3/P4 truss, with its two large solar arrays, will provide one-fourth of the total power generation capability of the completed station

The STS-115 crew visited KSC this week for a launch dress rehearsal, called the terminal countdown demonstration test The demonstration test provided the crew an opportunity to participate in various simulated countdown activities, and included equipment familiarization and emergency egress training

Mission managers will meet next week for a 2-day Flight Readiness Review, during which they will thoroughly assess the status of Space Shuttle Atlantis for launch This meeting will yield a number of key decisions about STS-115, including selection of an official launch date

Mission: STS-116 - 20th International Space Station Flight (12A 1) - P5 Truss Segment Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: No earlier than Dec 14, 2006 Launch Pad: 39B Crew: Polansky, Oefelein, Curbeam, Higginbotham, Patrick, Fuglesang and Williams Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Processing of Discovery for its next mission, STS-116, continues in Orbiter Processing Facility bay 3 The thermal barrier on the orbiter's rudder speed brake was replaced this week Testing of the power reactant storage and distribution system is under way, as are checkouts of the Ku-band antenna heater, the main propulsion system and the orbital maneuvering system pods Functional checkout of the radiator is complete The wheels and tires for the nose landing gear have been installed Windows no 3 and 4 were removed and replaced

Endeavour (OV-105)

Powered-up system testing continues on Endeavour in Orbiter Processing Facility bay 2 following an extensive modification period Freon coolant loop no 2 deservicing was completed this week Rigging and alignment of the remote manipulator system (orbiter arm) pedestals continue Workers completed verification of the orbiter's airlock/hatch Fuel tank installation for the power reactant storage and distribution (PRSD) system is under way Oxygen tank no 5 was installed last week, and leak checks were successfully completed this week The PRSD supplies liquid hydrogen and liquid oxygen to the orbiter's fuel cells, which serve as the electrical power plant for the vehicle

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: BULK_EMAIL

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list