Date: January 20th 2007

01 19 07

Jessica Rye Kennedy Space Center, Fla 321-867-2468

STATUS REPORT: S-011907

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads If you are a member of the media and would like further information, visit:
http://www nasa gov/centers/kennedy/news/index html

Mission: STS-117 - 21st International Space Station Flight (13A) - S3/S4 Truss Segment Solar Arrays Vehicle: Atlantis (OV-104) Location: Orbiter Processing Facility Bay 1 Launch Date: Targeted for March 16, 2007 Launch Pad: 39A Crew: Sturckow, Archambault, Reilly, Swanson, Forrester and Olivas Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Final vehicle closeouts are under way in preparation for technicians to move Atlantis to the Vehicle Assembly Building on Feb 7 This week, technicians worked to close out the forward reaction control system, the midbody and aft areas The payload bay doors were cycled and closed for flight The payload bay door strongbacks were removed Thursday Final orbiter power down is scheduled for Jan 25

Today, the external tank scheduled to fly with Atlantis, designated ET-124, was moved from the checkout cell in the Vehicle Assembly Building to be mated to the solid rocket boosters in high bay 1 Space Shuttle Program managers held a review on Tuesday and gave the "go ahead" to mate the tank with the boosters

Mission: STS-118 - 22nd International Space Station Flight (13A 1) - S5 Truss Segment Vehicle: Endeavour (OV-105) Location: Orbiter Processing Facility Bay 2 Launch Date: Targeted for June 28, 2007 Launch Pad: 39A Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Anderson Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Endeavour remains in Orbiter Processing Facility bay 2 and technicians continue preparing the vehicle for its first launch in just over four years The vehicle has undergone an extensive modification period, including the addition of all of the return-to-flight safety upgrades added to both Discovery and Atlantis

This week, technicians completed main propulsion system leak, functional and electrical checkouts Late Thursday, the first of three space shuttle main engines was installed The other two engines are scheduled to be installed today

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list