Date: February 10th 2007

02 09 07

Jessica Rye Kennedy Space Center, Fla 321-867-2468

STATUS REPORT: S-020907

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads If you are a member of the media and would like further information, visit:
http://www nasa gov/centers/kennedy/news/index html

Mission: STS-117 - 21st International Space Station Flight (13A) - S3/S4 Truss Segment Solar Arrays Vehicle: Atlantis (OV-104) Location: Vehicle Assembly Building High Bay 1 Launch Date: Targeted for March 15, 2007 Launch Pad: 39A Crew: Sturckow, Archambault, Reilly, Swanson, Forrester and Olivas Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

On Wednesday, Atlantis rolled from the Orbiter Processing Facility to the Vehicle Assembly Building, where it was lifted into high bay 1 and mated to the external fuel tank Orbiter power application is scheduled for Sunday Close-out operations continue on the fuel tank and solid rocket boosters, with thermal protection system foam trimming under way

The STS-117 payload is scheduled to be transferred to Launch Pad 39A on Monday The shuttle is set to roll out to the pad on Feb 14

Mission: STS-118 - 22nd International Space Station Flight (13A 1) - S5 Truss Segment Vehicle: Endeavour (OV-105) Location: Orbiter Processing Facility Bay 2 Launch Date: Targeted for June 28, 2007 Launch Pad: 39A Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Anderson Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

Endeavour remains in Orbiter Processing Facility bay 2, and technicians continue preparing the vehicle for its first launch in more than four years The vehicle has undergone an extensive modification period, including the addition of all of the return-to-flight safety upgrades added to both Discovery and Atlantis

This week, technicians installed fuel cell No 3 and completed fuel cell coolant loop servicing The shoulder installation for the orbiter boom sensor system, which is a robotic arm extension, was installed and final fit checks are complete

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list