STATUS REPORT: S-072007
NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT
Note: NASA's Kennedy Space Center issues Space Shuttle Processing
Status Reports periodically and is the source for information
regarding processing activities associated with the vehicles and
payloads
If you are a member of the media and would like further
information, visit:
http://www
nasa
gov/centers/kennedy/news/index
html
Mission: STS-118 - 22nd International Space Station Flight - S5 Truss Segment Vehicle: Endeavour (OV-105) Location: Launch Pad 39A Launch Date: Targeted for Aug 7, 2007 Launch Pad: 39A Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Drew Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
At Launch Pad 39A, preparations continue for the launch of Endeavour on STS-118
The orbiter's payload was installed on July 15 The helium signature test, which checks for leaks in the main propulsion system, is complete Technicians continue checking out the shuttle systems after finishing the external tank and solid rocket booster camera tests Work is under way to prepare for the loading of hypergolic propellants, which will begin July 23 These propellants will power the solid rocket booster hydraulic power units and Endeavour's orbital maneuvering system, forward reaction control system and auxiliary power units
Workers continue filling the liquid oxygen and liquid hydrogen storage tanks at the pad This fuel will be transferred to the external fuel tank shortly before launch Mating of the orbiter midbody umbilical unit, the connection point that allows for servicing of the orbiter's fuel cells, will be completed today
The STS-118 crew traveled to Kennedy Space Center this week to participate in the terminal countdown demonstration test, which includes a countdown dress rehearsal, emergency egress training and a checkout of the crew cabin configuration
Mission: STS-120 - 23rd International Space Station Flight - U S Node 2 Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: Targeted for Oct 20, 2007 Launch Pad: 39A Crew: Melroy, Zamka, Parazynski, Wheelock, Wilson, Nespoli and Tani Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
In Orbiter Processing Facility bay No 3, Discovery's main engines No 1 and 2 have been installed, as have the heat shields for those engines Engine cutoff sensor system and payload premate testing are complete Rigging of the latching mechanism for the orbiter boom sensor system is complete and the system has been installed for flight
Stacking of the STS-120 solid rocket boosters in the Vehicle Assembly Building began this week, with the left aft booster and left aft center segments delivered and mated to the mobile launch platform
Mission: STS-122 - 24th International Space Station Flight - Columbus Laboratory Module Vehicle: Atlantis (OV-104) Location: Orbiter Processing Facility Bay 1 Launch Date: Targeted for Dec 6, 2007 Launch Pad: 39A Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin and Walheim Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
In Orbiter Processing Facility bay No 1, the orbiter's dome heat shields and main engines have been removed The checkout of the forward reaction control system is complete Windows No 5 and 6 were removed and replaced The orbiter boom sensor system has been removed and inspected, with reinstallation set for next week
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: example@example.com
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]
If you're still having trouble, please contact the list owner at:
<mailto:list
admin@aus-city
com>
The following physical address is associated with this mailing list:
http://www aus-city com
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list