Date: July 21st 2007

07 20 07

George H Diller Kennedy Space Center, Fla 321-867-2468

STATUS REPORT: ELV-072007

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Phoenix Location: Payload Hazardous Servicing Facility Launch Pad: 17-A Launch Vehicle: Delta II 7925 Launch Date: Aug 3, 2007 Launch Time: 5:35:18 a m EDT

Mating of Phoenix to the upper-stage booster occurred Tuesday, July 17

Spacecraft engineers installed the heat shield onto the cruise stage Thursday, July 19 This was the last major milestone in spacecraft processing before going to the launch pad

Technicians are installing the integrated Phoenix payload into the payload transportation canister today

Phoenix will be transported to Pad 17-A for mating to the Delta II on Monday, July 23

At Pad 17-A, a simulated flight test of the Delta II was performed on Tuesday, July 17 This is an electrical and mechanical test of all events that the first and second stage of the vehicle will perform during ascent

A "LOX leak check" was conducted on Wednesday, July 18 This involves loading the Delta II first stage with liquid oxygen to verify its integrity and also serves as a countdown certification for the launch team

Mission: Dawn Location: Pad 17-B Launch Pad: 17-B Launch Vehicle: Delta II 7925-H Launch Timeframe: September

Dawn remains atop the Delta II launch vehicle at Pad 17-B The spacecraft will be removed from the launch vehicle on Saturday, July 21, and returned to the Astrotech payload processing facility near NASA's Kennedy Space Center

A firm date for launch is still being determined based on the launch window for the science of the mission, the availability of the Eastern Range and the necessary tracking, data and telemetry support The launch opportunity extends from Sept 7 to Oct 15

Previous status reports are available on the Web at:

http://www nasa gov/centers/kennedy/launchingrockets/status/2007

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list