STATUS REPORT: S-072707

NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT

Note: NASA's Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads If you are a member of the media and would like further information, visit:
http://www nasa gov/centers/kennedy/news/index html

Mission: STS-118 - 22nd International Space Station Flight - S5 Truss Segment Vehicle: Endeavour (OV-105) Location: Launch Pad 39A Launch Date: Aug 7, 2007 Crew: Kelly, Hobaugh, Williams, Morgan, Mastracchio, Caldwell and Drew Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

At Launch Pad 39A, preparations continue for the launch of Endeavour on STS-118 The hypergolic propellants have been loaded into the solid rocket booster hydraulic power units and Endeavour's orbital maneuvering system, forward reaction control system and the auxiliary power units Technicians have stowed the extravehicular mobility units (spacesuits) in the orbiter and are performing functional checkout of the suits Workers are also loading flight crew equipment and supplies into the crew cabin Closeout of the orbiter aft is under way The payload bay doors were opened today to allow for payload closeouts, including camera tests on the shuttle robotic arm and the extension, known as the orbiter boom sensor system

During the flight readiness review this week at Kennedy Space Center, NASA managers cleared STS-118 for flight and set an official launch date of Aug 7

Mission: STS-120 - 23rd International Space Station Flight - U S Node 2 Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: Targeted for Oct 20, 2007 Launch Pad: 39A Crew: Melroy, Zamka, Parazynski, Wheelock, Wilson, Nespoli and Tani Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

In Orbiter Processing Facility bay No 3, all three of Discovery's main engines have been installed, as have the heat shields for those engines Engine leak and functional tests are complete Technicians removed and replaced window No 7 The right-hand orbital maneuvering system pod has been delivered to the bay and preparations are under way for its installation next week

The STS-120 solid rocket boosters are being stacked in the Vehicle Assembly Building The external fuel tank for STS-120 is scheduled to arrive at KSC via barge from the Michoud Assembly Facility in New Orleans on Sunday The tank will be lifted into a checkout cell in the Vehicle Assembly Building on Monday

Mission: STS-122 - 24th International Space Station Flight - Columbus Module Vehicle: Atlantis (OV-104) Location: Orbiter Processing Facility Bay 1 Launch Date: Targeted for Dec 6, 2007 Launch Pad: 39A Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin and Walheim Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles

In Orbiter Processing Facility bay No 1, the orbiter boom sensor system has been removed, inspected and reinstalled in the orbiter Windows No 1, 2, 4, 5 and 6 have been removed and replaced The external tank door push test, which measures actuator performance, is complete Technicians are performing hypergolic fuel system testing on the orbital maneuvering system pods

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list