Date: July 31st 2007

07 30 07

John Yembrick Headquarters, Washington 202-358-0602 john yembrick-1@nasa gov

George Diller Kennedy Space Center, Fla 321-867-2468 george h diller@nasa gov

MEDIA ADVISORY: 40-07

NASA STARTS SPACE SHUTTLE ENDEAVOUR COUNTDOWN AUG 4

CAPE CANAVERAL, Fla - NASA will start the launch countdown for space shuttle Endeavour's STS-118 mission at 9 p m EDT Saturday, Aug 4, at the T-43 hour point The countdown includes 27 hours, 3 minutes of built-in hold time leading to a preferred launch time at approximately 7:02 p m EDT Tuesday, Aug 7 The launch window extends an additional five minutes

During the 11-day mission to the International Space Station, Endeavour's crew will add another truss segment to the expanding station, install a new gyroscope and add a spare parts platform The flight will have at least three spacewalks It also will debut a new system that enables docked shuttles to draw electrical power from the station to extend visits to the outpost

A detailed list of launch countdown milestones and times is available at:

http://www nasa gov/mission_pages/shuttle/news/index html

This mission is the 119th space shuttle flight, the 20th flight for Endeavour and the 22nd U S flight to the International Space Station The mission will be Endeavour's first flight in more than four years The shuttle has undergone extensive modifications, including the addition of safety upgrades already added to shuttles Discovery and Atlantis

For more information about the STS-118 crew and mission to the space station, visit:

http://www nasa gov/shuttle

-end-

STS-118 LAUNCH COUNTDOWN MILESTONES AND TIMES (All times Eastern)

Launch-3 Days (Saturday, Aug 4)

Prepare for the start of the STS-118 launch countdown Perform the call to stations (8:30 p m ) Countdown begins at the T-43 hour mark (9 p m ) Begin final vehicle and facility closeouts for launch Check out backup flight systems

Launch-2 Days (Sunday, Aug 5)

Review flight software stored in mass memory units and display systems Load backup flight system software into Endeavour's general purpose computers Remove flight-deck platforms (3 a m ) Activate and test navigational systems (10 a m ) Complete preparation to load power reactant storage and distribution system (12 p m ) Flight deck preliminary inspections complete (1 p m )

Enter first built-in hold at T-27 hours for duration of 4 hours (1 p m )

Clear launch pad of all non-essential personnel Perform test of the vehicle's pyrotechnic initiator controllers

Resume countdown (5 p m )

Launch-1 Day (Monday, Aug 6)

Enter 4-hour built-in hold at T-19 hours (1 a m )

Demate orbiter mid-body umbilical unit (1:30 a m ) Resume orbiter and ground support equipment closeouts Begin operations to load cryogenic reactants into Endeavour's fuel cell storage tanks (3 a m )

Resume countdown (5 a m )

Final preparations of the shuttle's three main engines for main propellant tanking and flight (5 a m ) Begin filling pad sound suppression system water tank (7 a m ) Pad sound suppression system water tank filling complete (10 a m ) Close out the tail service masts on the mobile launcher platform Begin star tracker functional checks (12:50 p m )

Enter planned hold at T-11 hours for 13 hours, 7 minutes (1 p m )

Activate orbiter's inertial measurement units Activate the orbiter's communications systems Install film in numerous cameras on the launch pad (1:55 p m ) Flight crew equipment late stow (6:10 p m ) Move Rotating Service Structure to the park position (10 p m ) Perform ascent switch list Fuel cell flow-through purge complete

Launch Day (Tuesday, Aug 7)

Resume countdown at T-11 hours (2:07 a m )

Activate the orbiter's fuel cells (3:17 a m ) Clear the blast danger area of all non-essential personnel Switch Endeavour's purge air to gaseous nitrogen (3:52 a m )

Enter planned 2-hour built-in hold at the T-6 hour mark (7:07 a m )

Launch team verifies no violations of launch commit criteria prior to cryogenic loading of the external tank Clear pad of all personnel

Resume countdown (9:07 a m )

Chill down propellant transfer lines (9:07 a m ) Begin loading the external fuel tank with about 500,000 gallons of cryogenic propellants (about 9:17 a m ) Complete filling the external tank with its flight load of liquid hydrogen and liquid oxygen propellants (about 12:07 p m ) Final Inspection Team proceeds to launch pad

Enter planned 3-hour built-in hold at T-3 hours (12:07 p m )

Perform inertial measurement unit preflight calibration Align Merritt Island Launch Area tracking antennas Perform open loop test with Eastern Range

Resume countdown at T-3 hours (3:07 p m )

Crew departs Operations and Checkout Building for the pad (3:12 p m ) Complete closeout preparations in the White Room Check cockpit switch configurations Flight crew begins entry into the orbiter (about 3:42 p m ) Astronauts perform air-to-ground voice checks with Launch and Mission Control Begin to close Endeavour's crew hatch (4:47 p m ) Begin Eastern Range final network open loop command checks Perform hatch seal and cabin leak checks Complete White Room closeout Closeout crew moves to fallback area Primary ascent guidance data is transferred to the backup flight system

Enter planned 10-minute hold at T-20 minutes (5:47 p m )

NASA test director conducts final launch team briefings Complete inertial measurement unit preflight alignments

Resume countdown at T-20 minutes (5:57 p m )

Transition the orbiter's onboard computers to launch configuration Start fuel cell thermal conditioning Close orbiter cabin vent valves Transition backup flight system to launch configuration

Enter estimated 46-minute hold at T-9 minutes (6:08 p m )

Launch director, Mission Management Team and NASA test director conduct final polls for "go/no go" to launch

Resume countdown at T-9 minutes (about 6:54 p m )

Start automatic ground launch sequencer (T-9 minutes) Retract orbiter crew access arm (T-7:30) Start mission recorders (T-6:15) Start Auxiliary Power Units (T-5) Arm solid rocket booster and external tank range safety safe and arm devices (T-5) Start liquid oxygen drainback (T-4:55) Start orbiter aerosurface profile test (T-3:55) Start main engine gimbal profile test (T-3:30) Pressurize liquid oxygen tank (T-2:55) Begin retraction of the gaseous oxygen vent arm (T-2:55) Fuel cells to internal reactants (T-2:35) Pressurize liquid hydrogen tank (T-1:57) Deactivate bi-pod heaters (T-1:52) Deactivate solid rocket booster joint heaters (T-1) Orbiter transfers from ground to internal power (T-0:50 seconds) Ground Launch Sequencer go for auto sequence start (T-0:31 seconds) Booster gimbal profile (T-0:21 seconds) Ignition of three space shuttle main engines (T-6 6 seconds) Booster ignition and liftoff (T-0)

CREW FOR MISSION STS-118 Commander: Scott Kelly Pilot: Charlie Hobaugh Payload Commander (MS1): Tracy Caldwell Mission Specialist (MS2): Rick Mastracchio Mission Specialist (MS3): Dave Williams Mission Specialist (MS4): Barbara R Morgan Mission Specialist (MS5): Alvin Drew

SUMMARY OF STS-118 LAUNCH DAY CREW ACTIVITIES Televised events (times may vary slightly) All times Eastern

Tuesday, Aug 7 8:30 a m --- Crew wakes up 12:55 p m --- Television coverage from crew quarters 2:32 p m --- Weather briefing 2:42 p m --- Don flight suits 3:12 p m --- Depart for launch pad 3:42 p m --- Arrive at White Room and begin ingress 4:57 p m --- Close crew hatch 7:02 p m --- Launch

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]

If you're still having trouble, please contact the list owner at:

<mailto:list
admin@aus-city
com>

The following physical address is associated with this mailing list:

http://www aus-city com

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list