Jan 11, 2008
Candrea Thomas Kennedy Space Center, Fla 321-867-2468 candrea k thomas@nasa gov
STATUS REPORT: S-011108
NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT
Note: NASA's Kennedy Space Center issues Space Shuttle Processing
Status Reports periodically and is the source for information
regarding processing activities associated with the vehicles and
payloads
If you are a member of the media and would like further
information, visit:
http://www
nasa
gov/centers/kennedy/news/index
html
Mission: STS-122 - 24th International Space Station Flight - Columbus laboratory Vehicle: Atlantis (OV-104) Location: Launch Pad 39A Launch Date: Targeting Feb 7 Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Launch Pad 39A - Engine cutoff (ECO) sensor external connector replacement hardware was cleared for installation and arrived at the pad Installation is tentatively scheduled to begin Saturday - Testing of the faulty ECO sensor system connector hardware continues at Marshall Space Flight Center - Space shuttle main engine ball seal leak checks performed Thursday with no issues - Ascent thrust vector controller No 2 was replaced Jan 5 and retested Jan 6 - Solid rocket booster hydraulic retest scheduled for today
Mission: STS-123 - 25th International Space Station Flight - Kibo, Dextre Vehicle: Endeavour (OV-105) Location: Orbiter Processing Facility Bay 2 Launch Date: Targeting Mid-March Launch Pad: 39A Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Orbiter Processing Facility bay No 2 - Shuttle orbiter galley functional checks completed today with no issues - Removal and replacement work will take place on the purge, vent and drain valve, which is part of the non-breathing air conditioning system, Jan 14-18 - Nose landing gear strut hydraulic level checks and pressurization for flight performed Wednesday - Main landing gear struts' weight on wheels leak check scheduled for Monday
Vehicle Assembly Building high bay No 1 - External tank/solid rocket booster mate in progress - External tank is hard mated - Closeout operations continue through this weekend - Preparation for ECO sensor external connector replacement will take place Saturday and Sunday
Mission: STS-124 - 26th International Space Station Flight - Kibo Pressurized Module, Japanese Remote Manipulator System Vehicle: Discovery (OV-103) Location: Orbiter Processing Facility Bay 3 Launch Date: Targeting April 24 Launch Pad: 39A Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide Inclination/Orbit Altitude: 51 6 degrees/122 nautical miles
Orbiter Processing Facility bay No 3 - Thermal control system checkout completed with no anomalies - Drag chute alignment and installation completed Thursday - Space shuttle main engine No 1 liquid oxygen transducer leak checks performed Thursday with nominal results - Solid rocket booster stacking date selection expected Jan 14 - Aft bulkhead check valve retest completed Wednesday with no issues
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: example@example.com
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
http://www aus-city com/cgi-bin/dada/mail cgi/list/[list]
If you're still having trouble, please contact the list owner at:
<mailto:list
admin@aus-city
com>
The following physical address is associated with this mailing list:
http://www aus-city com
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list