Oct 30, 2008
Allard Beutel Kennedy Space Center 321-867-2468 allard beutel@nasa gov
Don Savage/J D Harrington Headquarters, Washington 202-358-0183 donald l savage@nasa gov
Katherine Trinidad Headquarters, Washington 202-358-3749 katherine trinidad-1@nasa gov
MEDIA ADVISORY: 08-280
NASA MANAGERS DELAY HUBBLE SERVICING MISSION
WASHINGTON -- NASA managers have announced that they will not meet a February 2009 launch date for the fifth and final shuttle mission to the Hubble Space Telescope The decision comes after engineers completed assessments of the work needed to get a second data handling unit for the telescope ready to fly The unit will replace one that failed on Hubble in late September, causing the agency to postpone the servicing mission, which had been targeted for Oct 14
"We now have done enough analysis of all the things that need to happen with the flight spare unit to know that we cannot be ready for a February launch," said NASA's Astrophysics Division Director Jon Morse at NASA Headquarters in Washington "The February date was an initial estimate, assuming minimal hardware preparations and test durations that are no longer viewed as realistic We've communicated our assessment to the Space Shuttle Program so it can adjust near-term plans We will work closely with the Shuttle Program to develop details for a new launch opportunity "
"Getting ourselves in a position to be ready to launch the Hubble mission will involve many steps, and a significant one took place earlier today," said Hubble Program Manager Preston Burch at NASA's Goddard Space Flight Center in Greenbelt, Md "We held a flight certification peer review meeting where every aspect for doing this effort -- the inspections needed, all the tests to be conducted, the certification process and the final flight preparations -- was examined The conclusion was that we indeed have a very good plan in place "
The Hubble flight spare, known as the Science Instrument Command and Data Handling system, has been at Goddard since it was originally delivered as a back-up system in 1991 The unit currently is undergoing testing and examination to identify and correct any problems That work will continue until mid-December
The unit will then undergo environmental assessments that include electro-magnetic interference checks, vibration tests, and extended time in a thermal vacuum chamber Environmental testing is anticipated to run from mid-December to early March 2009 Final testing will be conducted on the unit, and delivery to NASA's Kennedy Space Center in Florida is expected in early April
"The equipment we are dealing with has a flight-proven design," said Burch " The original unit on Hubble ran for more than 18 years We have a lot of spare parts if we encounter problems, and we have most of the same test equipment that was used with the original unit We also have a lot of experience on our Hubble electrical replica, which uses the engineering model data handling unit "
The vast majority of the flight hardware, tools and support equipment that will be used during the mission will be stored at Kennedy A small amount of new work such as re-lubricating the latches on the Soft Capture Mechanism and testing the motors on the Flight Support System will be conducted The Wide Field Camera 3 will remain in its carrier The Cosmic Origins Spectrograph is in a special double-layered purge system in its shipping container to help support its environmental needs The new batteries to be installed during the mission are in cold storage at Goddard and will be returned to Kennedy in 2009
In the meantime, science observations on Hubble that had been suspended continue to move toward standard operations The current primary camera on the telescope, the Wide Field Planetary Camera 2, was brought back online On Wednesday, calibration images with the Advanced Camera for Surveys' Solar Blind Channel were completed Regular science observations resumed Thursday, and the first science image from the camera was released
For more information about Hubble, visit:
http://www nasa gov/hubble
For more information about the Space Shuttle Program, visit:
http://www nasa gov/shuttle
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: example@example.com
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/plugins/dada_bridge pl/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
<[program_url]/list/[list]>
If you're still having trouble, please contact the list owner at:
<mailto:[list_owner_email]>
The following physical address is associated with this mailing list:
[physical_address]
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list