STATUS REPORT: ELV-051509

EXPENDABLE LAUNCH VEHICLE STATUS REPORT

Mission: Lunar Reconnaissance Orbiter/Lunar Crater Observation and Sensing Satellite (LRO/LCROSS) Launch Vehicle: Atlas V Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla Launch Date: No earlier than June 17, 2009 Launch Window: TBD

NASA decided to move the LRO/LCROSS from a June 2 window to a June 17 window so as to allow the LCROSS team additional time to mitigate a potential thrust disturbance associated with the Atlas V Centaur fill/drain valves The Centaur is being used in a way that has never been done before While the Centaur hardware is designed and built to reliably perform its purpose of launching spacecraft, LCROSS is using the spent Centaur as a lunar impactor This reuse has posed technical challenges which the LCROSS team has had to address

At Launch Complex 41, the Atlas V launch vehicle was rolled from the Vertical Integration Facility to the launch pad in preparation for the wet dress rehearsal that is under way today The Atlas V is being fully loaded with propellants including liquid hydrogen, liquid oxygen and RP-1 fuel The launch vehicle will be rolled off the pad and returned to the Vertical Integration Facility on Saturday, May 16

At the Astrotech payload processing facility, LRO/LCROSS is being encapsulated into the Atlas V payload fairing today The spacecraft will be moved to the launch pad for integration with the Atlas V no earlier than May 21

Mission: Geostationary Operational Environmental Satellite (GOES-O) Launch Vehicle: Delta IV Launch Pad: Launch Complex 37, Cape Canaveral Air Force Station, Fla Launch Date: June 2009 Launch Window: TBD

On the Delta IV at Launch Complex 37, the three linear shape charges which are to be modified have been removed from the rocket Meanwhile, data from the second wet dress rehearsal and the flight program verification that followed are undergoing the customary review However, there appear to be no significant concerns

At the Astrotech Space Operations Facility, the GOES-O spacecraft is enclosed in the payload fairing The spacecraft remains in excellent health and is ready to be moved to the launch pad on June 6

NASA has contracted with Boeing to build and launch the GOES-O spacecraft The NASA Launch Services Program at Kennedy is supporting the launch in an advisory role NASA spacecraft project management for GOES-O is the responsibility of NASA's Goddard Space Flight Center After launch, once Boeing and NASA have completed on-orbit checkout and the spacecraft is operational, it will be turned over to NOAA

Previous status reports are available at:

http://www nasa gov/centers/kennedy/launchingrockets/status/index html

-end-

To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov



The following information is a reminder of your current mailing list subscription:

You are subscribed to the following list: [list_name]

using the following email: example@example.com

You may automatically unsubscribe from this list at any time by visiting the following URL:

http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/

If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism

You may also change your subscription by visiting this list's main screen:

<[program_url]/list/[list]>

If you're still having trouble, please contact the list owner at:

<mailto:[list_owner_email]>

The following physical address is associated with this mailing list:

[physical_address]

Forward to a Friend
 
  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Shuttle / ISS Status Report list

Privacy Policy:

Private list