RELEASE: 09-134
NASA'S ARES I-X ROCKET ACHIEVES HISTORIC HARDWARE MILESTONES
CAPE CANAVERAL, Fla -- NASA's Constellation Program reached two major processing milestones this week as two new pieces of Ares I-X hardware were transferred for final assembly in preparation for the first flight test of the rocket later this summer at NASA's Kennedy Space Center in Florida
Once stacking operations begin later this month, it will be the first time a new vehicle has been stacked on NASA's Mobile Launcher Platform in more than 25 years
The forward assembly, composed of the forward skirt, forward skirt extension and the frustum, was moved Thursday from Kennedy's Assembly Refurbishment Facility, or ARF, to the Vehicle Assembly Building for stacking operations
The aft skirt was moved Monday from the ARF to the Rotation Processing and Surge Facility to be attached to the aft motor segment, forming the aft assembly The assembly will next move to the Vehicle Assembly Building for stacking on the Mobile Launcher Platform
The Ares I-X rocket is a combination of existing and simulator hardware that will resemble the Ares I crew launch vehicle in size, shape and weight It will provide valuable flight data to guide the final design of the Ares I, which will launch astronauts in the Orion crew exploration vehicle
"This is a very exciting week for the team to have the hardware moving out of the ARF, showing how much progress we've made and that we are that much closer to launch," said NASA Ares I-X mission manager Bob Ess of NASA's Johnson Space Center in Houston
The flight test of the Ares I-X will bring NASA one step closer to its Constellation Program's exploration goals of returning humans to the moon for sustained exploration of the lunar surface and missions to destinations beyond
The forward assembly connects the 12-foot diameter first stage motor to the 18-foot diameter upper stage simulator Weighing more than 40,000 pounds, the assembly houses three newly designed descent parachutes for first stage recovery
The aft skirt, which is used at the bottom of the Solid Rocket Boosters for the Space Shuttle Program, was modified over the last year and a half for use on Ares I-X Some modifications include adding deceleration and tumble motors, avionics and a controller for the auxiliary power unit
"This week is the culmination of tremendous hard work and dedication by the entire NASA and contractor team," said Joe Oliva, first stage program manager for the Ares I-X at ATK Space Systems in Salt Lake City "These milestones are leading us to a flight test later this year that will provide our proof of concept data for NASA's next generation of launch vehicles "
United Space Alliance, of Houston, under a subcontract to ATK completed the processing and integration of the forward assembly and aft skirt ATK is NASA's prime contractor for the first stage of the Ares I rocket
Video B-roll of the arrival of the Ares I-X hardware will be available on NASA Television's Video File feed For NASA TV streaming video, schedules and downlink information, visit:
http://www nasa gov/ntv
For more information about the Ares I-X and NASA next-generation spacecraft, visit:
http://www nasa gov/ares
-end-
To subscribe to the list, send a message to: ksc-subscribe@newsletters nasa gov To remove your address from the list, send a message to: ksc-unsubscribe@newsletters nasa gov
The following information is a reminder of your current mailing list subscription:
You are subscribed to the following list: [list_name]
using the following email: example@example.com
You may automatically unsubscribe from this list at any time by visiting the following URL:
http://www aus-city com/cgi-bin/dada/mail cgi/u/[list]/
If the above URL is inoperable, make sure that you have copied the entire address Some mail readers will wrap a long URL and thus break this automatic unsubscribe mechanism
You may also change your subscription by visiting this list's main screen:
<[program_url]/list/[list]>
If you're still having trouble, please contact the list owner at:
<mailto:[list_owner_email]>
The following physical address is associated with this mailing list:
[physical_address]
This mailing list is announce-only.
Shuttle / ISS Status Report list
Private list